Liebherr-Mischtechnik GmbH, 88427 Bad Schussenried, Germany

Mixing plants produce 2 million cbmof concrete in 18 months

Four Liebherr Betomix 4.5 mixing plants are producing the concrete for one of the largest dam projects in South-East Asia, the dam in the province Son La in North-West Vietnam. The 2,400 megawatt power station, a dam with a height of 140 m, is scheduled to go on-line by 2012. The first concrete was produced and poured in January 2008. In only 18 months since then, 2 million cbm of quality concrete have been manufactured and processed. The left side of the Son La dam has already been concreted to the full height.