XXL format roof trusses

A challenge for production, logistics and assembly

Manufacturing each of the more than 40 metre long concrete behemoths weighing about 68 tonnes was anything but an everyday occur- rence. Yet, the greater challenge was of a logistical nature. The eleven trusses, which were to form the roof of a production hall, also had to be transported individually and laboriously to the site. They were manoeuvred at night and at times through narrow towns or route sections with steep gradients and sharp curves. Perfect timing was the decisive factor in routing the heavy transport on its 90 km long journey.

Subscribe to magazine

Contact

Günther GmbH + Co. KG Bauunternehmung Sohlstättenweg 2 57250 Netphen, Deutschland T +49 2737 5090 F +49 2737 244 info@guentherbau.net www.guentherbau.net Howal GmbH Am Reutgraben 4 76275 Ettlingen, Deutschland T +49 7243 949730 F +49 7243 90645 info@howal.com www.howal.de

Events

29.04.2024 - 01.05.2024
05.05.2024 - 09.05.2024
07.05.2024 - 09.05.2024